(Reprinted with amendments adopted on April 21, 2025)
FIRST REPRINT
A.B. 529
-
*AB529_R1*
ASSEMBLY BILL NO. 529–COMMITTEE
ON GROWTH AND INFRASTRUCTURE
(ON BEHALF OF THE JOINT INTERIM STANDING COMMITTEE
ON GROWTH AND INFRASTRUCTURE)
MARCH 24, 2025
____________
Referred to Committee on Growth and Infrastructure
SUMMARY—Revises provisions governing facilities for the
generation of electricity. (BDR 58-427)
FISCAL NOTE: Effect on Local Government: No.
Effect on the State: No.
~
EXPLANATION – Matter in bolded italics is new; matter between brackets [omitted material] is material to be omitted.
AN ACT relating to energy; requiring certain wholesale facilities for
the generation of electricity to purchase power from
certain small electric utilities; requiring a provider of
electric service that serves a wholesale generation facility
in the service territory of certain small electric utilities to
make certain payments to the utility; and providing other
matters properly relating thereto.
Legislative Counsel’s Digest:
Existing law provides for the issuance of a certificate of public convenience
1
and necessity to certain cooperative associations, nonprofit corporations and
2
nonprofit associations that provide electric service to their members. (NRS
3
704.677) Existing law also authorizes certain local governmental entities to provide
4
electric service. (Chapters 709 and 710 of NRS) This bill requires certain wholesale
5
facilities for the generation of electricity which are located within the service
6
territory of such a cooperative association, nonprofit corporation or nonprofit
7
association or municipal utility to purchase the energy required to operate, maintain
8
or repair the facility from the cooperative association, nonprofit corporation or
9
nonprofit association or municipal utility. This bill further requires the facility to:
10
(1) adhere to all rules, rates and policies established by the governing board of the
11
cooperative association, nonprofit corporation or nonprofit association or municipal
12
utility relating to the delivery of and payment for power; and (2) authorize a
13
cooperative association, nonprofit corporation or nonprofit association or municipal
14
utility to install or certify the proper operation of a meter to accurately measure and
15
provide accurate monthly readings of the energy use of the facility. This bill
16
further: (1) authorizes a cooperative association, nonprofit corporation, nonprofit
17
– 2 –
-
*AB529_R1*
association or municipal utility to charge certain rates to the wholesale generation
18
facility; and (2) requires a provider of electric service that provides power to a
19
wholesale generation facility in the service territory of the cooperative association,
20
nonprofit corporation, nonprofit association or municipal utility to make certain
21
payments to the cooperative association, nonprofit corporation, nonprofit
22
association or municipal utility.
23
THE PEOPLE OF THE STATE OF NEVADA, REPRESENTED IN
SENATE AND ASSEMBLY, DO ENACT AS FOLLOWS:
Section 1. Chapter 701 of NRS is hereby amended by adding
1
thereto a new section to read as follows:
2
1. A wholesale generation facility in this State which becomes
3
operational on or after January 1, 2026, and is located within the
4
service territory of a rural electric utility shall:
5
(a) Purchase its station power from the rural electric utility,
6
unless otherwise provided in a written agreement between the
7
wholesale generation facility and the rural electric utility.
8
(b) Adhere to all rules, rates and policies established by the
9
governing board of the rural electric utility relating to the delivery
10
of and payment for station power.
11
(c) Authorize the rural electric utility to install or certify the
12
proper operation of a meter that measures the use of station power
13
by a wholesale generation facility and provides the rural electric
14
utility with accurate monthly readings of that use.
15
2. A rural electric utility may charge to a wholesale
16
generation facility a retail rate for station power which is
17
commensurate with the rate the rural electric utility charges to
18
customers in its service territory with comparable load
19
magnitudes, load factors and other relevant characteristics.
20
3. If a wholesale generation facility receives station power
21
from a provider of electric service other than the rural electric
22
utility for the service territory in which the wholesale generation
23
facility is located, the provider of electric service shall remit to the
24
rural electric utility an amount equal to the payment which the
25
wholesale generation facility would have paid for such station
26
power if provided by the rural electric utility.
27
4. As used in this section:
28
(a) “Municipal electric utility” includes, without limitation:
29
(1) An electric utility established pursuant to chapter 709 or
30
710 of NRS.
31
(2) Any other electric utility that is owned, operated or
32
controlled by a county, city or other local governmental entity.
33
(b) “Rural electric utility” means:
34
– 3 –
-
*AB529_R1*
(1) A cooperative association, nonprofit corporation,
1
nonprofit association or provider of electric service which is
2
declared to be a public utility pursuant to NRS 704.673 and which
3
provides service only to its members; or
4
(2) A municipal electric utility which provides electric
5
service to fewer than 100,000 retail electric meters.
6
(c) “Station power” means energy used on the site of a
7
wholesale generation facility for the operation, maintenance or
8
repair of the facility, including, without limitation, energy used for
9
lighting, thermal regulation, fuel processing and powering
10
equipment. The term:
11
(1) Includes any such load:
12
(I) That is served by a provider of electric service over a
13
distribution line that is connected to the system of the provider of
14
electric service at a point that is separate from the switchyard
15
where a generation or storage resource of the wholesale
16
generation facility is connected to the transmission system; or
17
(II) That is served by the system of a provider of electric
18
service that is connected to the transmission system at the same
19
point as a generation or storage resource of the wholesale
20
generation facility during any period when the generation or
21
storage resource is idle.
22
(2) With respect to a wholesale generation facility which
23
generates electricity from geothermal resources, does not include
24
energy used to operate fans or pumps or parasitic loads associated
25
with the production of electricity from a geothermal resource.
26
(d) “Wholesale generation facility” means a facility for the
27
generation of electricity that has a capacity in excess of 1
28
megawatt and:
29
(1) Is not affiliated through common ownership with an
30
end-use customer that purchases electricity; and
31
(2) Does not provide the electricity generated by the facility
32
directly and exclusively to the end-use customer described in
33
subparagraph (1).
34
Sec. 2. 1. This section becomes effective upon passage and
35
approval.
36
2. Section 1 of this act becomes effective:
37
(a) Upon passage and approval for the purpose of adopting any
38
regulations and performing any other preparatory administrative
39
tasks that are necessary to carry out the provisions of this act; and
40
(b) On January 1, 2026, for all other purposes.
41
H
Important: This plain English summary was generated by AI and is provided for informational purposes only.
It is not legal advice. Always consult the official bill text on LegiScan
or a qualified attorney for legal matters.