Nevada
AB505
AB505 - Revises provisions relating to constructional defects. (BDR 3-1144)
Source: LegiScan ·
4,672 words in original text
Plain English summary not yet available
The full original text is available below. Check back soon as we process this bill.
A.B. 505
-
*AB505*
ASSEMBLY BILL NO. 505–COMMITTEE ON JUDICIARY
MARCH 24, 2025
____________
Referred to Committee on Commerce and Labor
SUMMARY—Revises provisions relating to constructional defects.
(BDR 3-1144)
FISCAL NOTE: Effect on Local Government: No.
Effect on the State: No.
~
EXPLANATION – Matter in bolded italics is new; matter between brackets [omitted material] is material to be omitted.
AN ACT relating to constructional defects; requiring a written
response to a notice of a constructional defect to include
certain information; requiring a contractor, subcontractor
and certain related professionals to maintain a policy of
insurance which covers liability for constructional
defects; revising provisions relating to certain settlement
offers concerning constructional defects; clarifying
certain provisions relating to the recovery of damages
proximately caused by a constructional defect; revising
provisions relating to certain required mediation; revising
the definitions of certain terms related to actions resulting
from constructional defects; and providing other matters
properly relating thereto.
Legislative Counsel’s Digest:
Existing law authorizes an owner of a residence or appurtenance and certain
1
other persons to commence a civil action against a contractor, subcontractor,
2
supplier or design professional for certain constructional defects in the residence or
3
appurtenance. (NRS 40.610, 40.640, 40.645) Under existing law, before a claimant
4
commences an action or amends a complaint to add a cause of action for a
5
constructional defect, the claimant must give written notice to the contractor and
6
the matter must be submitted to mediation unless mediation is waived in writing.
7
(NRS 40.645) Existing law also requires a contractor, subcontractor, supplier or
8
design professional who receives notice of a constructional defect to send a written
9
response to the claimant within 90 days after receiving the notice. (NRS 40.6472)
10
Section 3 of this bill: (1) requires the written response to state whether the
11
contractor, subcontractor, supplier or design professional has elected to enter into
12
mediation or waive mediation in writing; and (2) provides that failure to include
13
such a statement shall be deemed a written waiver of the requirement to submit the
14
– 2 –
-
*AB505*
matter to mediation. Section 3 also requires the written response to include certain
15
additional information if the contractor, subcontractor, supplier or design
16
professional has elected to repair the constructional defect. Section 8 of this bill
17
revises provisions governing the mediation required by existing law by: (1)
18
providing that such mediation must be waived in writing on or before the deadline
19
for the submission of the written response required by section 3; and (2) removing
20
language prohibiting the total fees for each day of mediation from exceeding $750.
21
Existing law authorizes, but does not require, a contractor, subcontractor,
22
supplier or design professional who receives written notice of a constructional
23
defect to present the claim to an insurer. (NRS 40.649) Section 4 of this bill
24
requires a contractor, subcontractor, supplier and design professional to: (1)
25
maintain a policy of insurance which covers liability for constructional defects; and
26
(2) present the claim to the insurer that issued the policy.
27
Existing law establishes a procedure by which a claimant and a contractor,
28
subcontractor, supplier or design professional may agree to have a judgment
29
entered before the claimant commences a civil action for the constructional defect
30
or amends a complaint to add a cause of action for the constructional defect. (NRS
31
40.652) Sections 5 and 10 of this bill revise this procedure and eliminate certain
32
penalties for the rejection of a settlement offer for consistency with Rule 68 of the
33
Nevada Rules of Civil Procedure and certain other provisions of existing law
34
relating to settlement offers. Sections 6 and 7 of this bill make conforming changes
35
by removing references to the provision repealed by section 10 and certain related
36
language. Section 6 also clarifies that any interest recoverable as damages in a
37
cause of action for a constructional defect must be provided by statute for damages
38
otherwise recoverable by the claimant. (NRS 40.655)
39
Sections 1 and 2 of this bill revise the definitions of certain terms applicable to
40
actions resulting from constructional defects.
41
THE PEOPLE OF THE STATE OF NEVADA, REPRESENTED IN
SENATE AND ASSEMBLY, DO ENACT AS FOLLOWS:
Section 1. NRS 40.615 is hereby amended to read as follows:
1
40.615 “Constructional defect” means a defect in the design,
2
construction, manufacture, repair , alteration or landscaping of a
3
[new] residence [, of] or appurtenance or a defect in an [alteration
4
of or] addition to [an existing] a residence [, or of an appurtenance
5
and includes, without limitation, the design, construction,
6
manufacture, repair or landscaping of a new residence, of an
7
alteration of or addition to an existing residence,] or [of] an
8
appurtenance:
9
1. Which presents an unreasonable risk of injury to a person or
10
property; or
11
2. Which is not completed in compliance with any applicable
12
building code and in a good and workmanlike manner in
13
accordance with the generally accepted standard of care in the
14
industry for that type of repair and [proximately] :
15
(a) Proximately causes physical damage to the residence, an
16
appurtenance or the real property to which the residence or
17
appurtenance is affixed [.] ; or
18
– 3 –
-
*AB505*
(b) Creates a substantial risk of causing the damage described
1
in paragraph (a).
2
Sec. 2. NRS 40.630 is hereby amended to read as follows:
3
40.630 1. “Residence” means any dwelling in which title to
4
the [individual units] unit is transferred to the owners.
5
2. As used in this section, “dwelling” includes a single-family
6
house.
7
Sec. 3. NRS 40.6472 is hereby amended to read as follows:
8
40.6472 1. Except as otherwise provided in NRS 40.670 and
9
40.672, a written response must be sent by certified mail, return
10
receipt requested, to a claimant who gives notice of a constructional
11
defect pursuant to NRS 40.645:
12
(a) By the contractor not later than 90 days after the contractor
13
receives the notice; and
14
(b) If notice was sent to a subcontractor, supplier or design
15
professional, by the subcontractor, supplier or design professional
16
not later than 90 days after the date that the subcontractor, supplier
17
or design professional receives the notice.
18
2. The written response sent pursuant to subsection 1 must
19
respond to each constructional defect in the notice and:
20
(a) Must state whether the contractor, subcontractor, supplier or
21
design professional has elected to [repair] :
22
(1) Repair the defect or cause the defect to be repaired. [If an
23
election to repair is included in the response and the repair will
24
cause the claimant to move from the claimant’s home during the
25
repair, the election must also include monetary compensation in an
26
amount reasonably necessary for temporary housing or for storage
27
of household items, or for both, if necessary.]
28
(2) Enter into mediation or waive mediation in writing
29
pursuant to NRS 40.680. Failure to include the statement required
30
by this subparagraph in the written response shall be deemed a
31
written waiver of the requirement to submit the matter to
32
mediation pursuant to NRS 40.680.
33
(b) [May] Except as otherwise provided in paragraph (a) of
34
subsection 3, may include a proposal for monetary compensation,
35
which may include contribution from a subcontractor, supplier or
36
design professional.
37
(c) May disclaim liability for the constructional defect and state
38
the reasons for such a disclaimer.
39
3. In addition to the requirements prescribed by subsection 2,
40
if an election to repair is included in the written response sent
41
pursuant to subsection 1, the written response must:
42
(a) Include a proposal for monetary compensation in an
43
amount reasonably necessary for temporary housing or for
44
– 4 –
-
*AB505*
storage of household items, or both, if the repair will cause the
1
claimant to move from the claimant’s home during the repair;
2
(b) Specify in reasonable detail the:
3
(1) Defect to be repaired;
4
(2) Method to be used to repair the defect; and
5
(3) Nature and extent of the repair; and
6
(c) Reasonably identify the proximate location of the defect to
7
be repaired.
8
4. If the claimant is a homeowners’ association, the association
9
shall send a copy of the response to each member of the association
10
not later than 30 days after receiving the response.
11
[4.] 5. If the contractor, subcontractor, supplier or design
12
professional has elected not to repair the constructional defect, the
13
claimant or contractor may bring a cause of action for the
14
constructional defect or amend a complaint to add a cause of action
15
for the constructional defect.
16
[5.] 6. If the contractor, subcontractor, supplier or design
17
professional has elected to repair the constructional defect, the
18
claimant must provide the contractor, subcontractor, supplier or
19
design professional with a reasonable opportunity to repair the
20
constructional defect.
21
Sec. 4. NRS 40.649 is hereby amended to read as follows:
22
40.649 1. [If a] A contractor, subcontractor, supplier or
23
design professional shall maintain a policy of insurance which
24
covers liability for acts or omissions actionable pursuant to NRS
25
40.600 to 40.695, inclusive.
26
2. A
contractor,
subcontractor,
supplier
or
design
27
professional who receives written notice of a constructional defect
28
[, the contractor, subcontractor, supplier or design professional may]
29
shall present the claim to [an] the insurer which has issued [a] the
30
policy of insurance [that covers all or any portion of the business of
31
the contractor, subcontractor, supplier or design professional.
32
2. If the contractor, subcontractor, supplier or design
33
professional presents the] required by subsection 1.
34
3. An insurer that receives a claim [to the insurer] pursuant to
35
[this section, the insurer:] subsection 2 must:
36
(a) [Must treat] Treat the claim as if a civil action has been
37
brought against the contractor, subcontractor, supplier or design
38
professional; and
39
(b) [Must provide] Provide coverage to the extent available
40
under the policy of insurance as if a civil action has been brought
41
against
the
contractor,
subcontractor,
supplier
or
design
42
professional.
43
[3. A contractor, subcontractor, supplier or design professional
44
is not required to present a claim to the insurer pursuant to this
45
– 5 –
-
*AB505*
section, and the failure to present such a claim to the insurer does
1
not relieve the insurer of any duty under the policy of insurance to
2
the contractor, subcontractor, supplier or design professional.]
3
Sec. 5. NRS 40.652 is hereby amended to read as follows:
4
40.652 1. At any time after a claimant has given notice
5
pursuant to NRS 40.645 and before the claimant commences an
6
action or amends a complaint to add a cause of action for a
7
constructional defect against a contractor, subcontractor, supplier or
8
design professional, the claimant or any contractor, subcontractor,
9
supplier or design professional who has received notice pursuant to
10
NRS 40.645 or 40.646 may serve upon one or more other parties a
11
written offer to allow judgment to be entered without action in
12
accordance with the terms and conditions of the offer of judgment.
13
Except as otherwise provided in subsection 7, any such written
14
offer must be unconditional and for a set amount.
15
2. Except as otherwise provided in subsection 7, if, within [10]
16
14 days after the date of service of an offer of judgment, the party to
17
whom the offer was made serves written notice that the offer is
18
accepted, the party who made the offer or the party who accepted
19
the offer may file the offer, the notice of acceptance and proof of
20
service with the clerk of the district court. Upon receipt by the clerk,
21
the clerk shall enter a judgment according to the terms of the offer.
22
Any judgment entered pursuant to this section shall be deemed a
23
compromise settlement. The judgment, the offer, the notice of
24
acceptance and proof of service, with the judgment endorsed,
25
become the judgment roll.
26
3. If the offer of judgment is not accepted pursuant to
27
subsection 2 within [10] 14 days after the date of service, the offer
28
shall be deemed rejected by the party to whom it was made and
29
withdrawn by the party who made it. The rejection of an offer does
30
not preclude any party from making another offer pursuant to this
31
section. Evidence of a rejected offer is not admissible in any
32
proceeding other than a proceeding to determine costs and fees.
33
4. Except as otherwise provided in this section, if a party who
34
rejects an offer of judgment fails to obtain a more favorable
35
judgment in an action for a constructional defect, the court:
36
(a) May not award to the party any costs or attorney’s fees;
37
(b) May not award to the party any interest on the judgment for
38
the period from the date of service of the offer to the date of entry of
39
the judgment;
40
(c) Shall order the party to pay the taxable costs incurred by the
41
party who made the offer; and
42
(d) May order the party to pay to the party who made the offer
43
any or all of the following:
44
– 6 –
-
*AB505*
(1) A reasonable sum to cover any costs incurred by the party
1
who made the offer for each expert witness whose services were
2
reasonably necessary to prepare for and conduct the trial of the case.
3
(2) Any applicable interest on the judgment for the period
4
from the date of service of the offer to the date of entry of the
5
judgment.
6
(3) Reasonable attorney’s fees incurred by the party who
7
made the offer for the period from the date of service of the offer to
8
the date of entry of the judgment. If the attorney of the party who
9
made the offer is collecting a contingent fee, the amount of any
10
attorney’s fees awarded
[Text truncated for display. Full text available on LegiScan.]
Important: This plain English summary was generated by AI and is provided for informational purposes only.
It is not legal advice. Always consult the official bill text on LegiScan
or a qualified attorney for legal matters.